On-going works to complete the new toilet block and store room. Now down to fitting out and more minor works. |
2 February 2025 Forming the walkway. (Photo courtesy Brian Haigh) |
9 February 2025 Installing the cubicles. (Photo courtesy Brian Haigh) |
Tiling above the washbasins. (Photo courtesy Brian Haigh) |
Whacking the scalpings forming the base for concreting. |
Martin 'nibbling'. (Photo courtesy Brian Haigh) |
It fits. (Photo courtesy Brian Haigh) |
25 February 2025 Concreting the outside walkway. Dumper brings the concrete from the Mixer. (Photo courtesy Brian Haigh) |
Levelling the concrete. (Photo courtesy Brian Haigh) |
Too much here. (Photo courtesy Brian Haigh) |
More levelling. (Photo courtesy Brian Haigh) |
A well earned rest before the final finish is applied to give a better grip during wet weather. (Photo courtesy Brian Haigh) |
Railings arrived. (Photo courtesy Brian Haigh) |
Railings erected on walkway. (Photo courtesy Brian Haigh) |
Goodbye to the old loos! (Photo courtesy Brian Haigh) |
And a great relief to welcome the new toilet block and storeroom! |
Many volunteers helped with various stages of construction. Kelvin & John in front of the (almost) completed project. Now largely a matter of tidying up, completing the area in front of the block and laying a path to the rear. |