For a history of the construction of the replacement toilet block and donate towards this vital project please see HERE |
23 January 2024 Slating over the main part of the new Toilet Block is now complete. A small number of slates and the ridge to be finished on the store room area. |
28 January 2024 Roof is now complete! Onto the internal works, drains and more... |
30 January 2024 A sewerage pump is required as the Septic Tank level is unfavourable. The cylinder is seen in its hole and being surrounded by concrete (with the inside containing a slightly larger amount of water to maintain its shape). |
18 February 2024 Digging a trench for the sewerage pipe from the pump towards the Septic Tank (Photo courtesy Brian Haigh) |
18 February 2024 |
25 February 2024 Sewerage pipe (Photo courtesy Brian Haigh) |
Floor insulation going down. (Photo courtesy Brian Haigh) |
Pipe and pump connected. (Photo courtesy Brian Haigh) |
28 February 2024 Membrane above floor insulation in preparation for screeding. (Photo courtesy Brian Haigh) |
28 February 2024 (Photo courtesy Brian Haigh) |
28 February 2024 Floor screeding begins. (Photo courtesy Brian Haigh) |
05 March 2024 Trench to the Septic Tank complete and awaiting a final connection in the future. (Photo courtesy Brian Haigh) |
No Entry - Floor screed drying!. (Photo courtesy Brian Haigh) |
A look inside. (Photo courtesy Brian Haigh) |
07 April 2024 Toilet Block - internal works continue and Dagger Boards being added. |
06 June 2024 Security door for the Storeroom has arrived. Frame in course of being installed. |
23 July 2024 Security door for the Storeroom now fixed and locked. Internal works including Ceiling and Roof Insulation, Electrical works together with painting both inside and outside are in progress. |
15 September 2024 More painting. (Photo courtesy Brian Haigh) |
(Photo courtesy Brian Haigh) |
BACK |